Roadworks Update for Nicholls Street 29

26/08/24 – 30/08/24 (Mon- Fri)
• Traffic management:
Dudley street:
Two lanes open between Nicholls Street and Slater Street. Both sides of footpaths on Dudley Street are open
7am-6pm
Stapletons Road/Dudley St intersection road closure:
6pm-7am, one way between Nicholls and Stapletons, no entry from Stapletons Rd and Stapleton Road return two lanes
• Dudley berm reshape, landscape
• Install tactile pavers on footpath
• Pavers installation at Dudley/Stapletons intersection
Site contact person:
Kane Radcliffe, Site supervisor, M:021 830 670
Take a look at what is happening around Richmond
Pickup and Plant at Pareawa Banks Avenue School Entrance August
This school walkway at the Northern entrance of Pareawa Banks Avenue School needs tidying. So we ran a working bee!
Matariki 2026
Matariki 2026 was a beautiful community celebration held in the Richmond Community Garden.
Pickup and Plant at Pareawa Banks Avenue School Entrance June
This school walkway at the Northern entrance of Pareawa Banks Avenue School needs tidying. So we ran a working bee!
Petrie Park Plant and Tidy June Session
Neighbours came together to plant fruit trees and to clean up two crop circles in Petrie Park. Followed by hot soup and a cuppa.
Matariki Community Weaving Session
A morning of meaningful weaving to create kites/ manu tukutuku to decorate our Ururangi Matariki tree.
Red Zone Edge Housing Forum
At the Red Zone Housing Forum, guest speakers covered future Red Zone housing topics, then those attending wrote down what should and shouldn’t be in the Red Zone edge housing areas.