Roadworks Update for Nicholls Street 23
We’ve made significant progress thanks to a break in the weather after a month of rain. We began sealing the footpaths last Thursday, and both sides should be sealed by the end of Tuesday, 09/07/24. Following this, there will be major traffic management changes on both streets. The topsoil is still quite fresh at the moment. I know it looks fluffy, but please avoid leaving footprints on it at this stage. Thanks for your cooperation.
Starting Wednesday, 10/07/24, Nicholls Street will open to two-lane traffic, allowing residents to enter and exit from North Avon Road. The landscaping crew will continue working on both sides of Nicholls Street, which may require pedestrian escorts or shoulder closures. Road sweeping may also occur this week, so please drive carefully.
We will be closing Dudley Street between Slater Street and Stapletons Road. If residents living on Dudley Street need daytime urgent access to Dudley Street, please approach from Nicholls Street, where a full-time Traffic Controller will assist you. However, please note that driving on a closed road may void your insurance in case of damage. You can alternatively park nearby and use the footpath on the north side between the trees and fences on Dudley Street.
We plan to pour the kerb between Nicholls Street and Slater Street (south side) on Wednesday, 10/07/24. Residents at 30, 32, and 34 Dudley Street, please move your vehicles by 7 AM. Driveway access will be restored by 5.30 PM.
Traffic:
08/07/24 – 09/07/24 (Mon – Tues)
• Road closure on Dudley street between Nicholls Street and Stapleton Road and will return to one-way traffic after 5:30 PM.
• One-way entry from Slater Street, NO entry from North Avon Road
10/07/24 – 12/07/24 (Wed – Fri)
• Nicholls Street will be open to residents with two lanes. Residents can enter/exit from North Avon Road.
• Please be mindful of landscaping crews working on the street and footpath.
• Dudley Street will be completely closed from 7:00 AM to 5:30 PM and will return to one-way traffic after 5:30 PM. We will try our best to accommodate residents on Dudley Street.
If you need daytime access, please approach from Nicholls Street, where a full-time Traffic Controller will be available to assist you.
• Site investigation work on Dudley Street will produce significant noise when the large air vac is in operation.
• Kerb pouring on Wednesday, weather permitting, 10/07/24, between Slater Street and Nicholls Street on the south side.
Site contact person:
Kane Radcliffe, Site supervisor, M:021 830 670
Take a look at what is happening around Richmond
Petrie Park Mural Painting Event 3
Our second Petrie Park mural painting day with the community was a success, and even the dogs came along!
Petrie Park Mural Painting Event 2
Our second Petrie Park mural painting day with the community was a success, and even the dogs came along!
Petrie Park Mural Painting Event I
We had our first mural painting day with the community and it was a success!
Matariki 2024 — A Day and Night of Connection
Matariki in the Zone was a wonderful day and evening out for our community. A big thank you to Avon-Ōtākaro Network Richmond Community Garden and Avebury House for running this every year! We are Richmond hopped on the bandwagon to help out more this year. So...
Thank you and Farewell to David Duffy
Thank you David for all of your hard work as an integral member of the Richmond Resident’s and Business Association (We Are Richmond) since 2018.
New Richmond Village Sign Completed
What's in a Sign? Well, a lot! After years of deteriorating in the elements, having broken and faded signs, and causing the shopping centre to look run down, We are Richmond decided to do something about the Richmond Village Sign. The shopping centre has no body...