Stapletons Road (Warden St to Shirley Rd)
- COMPLETED
- Drainage completed
- Western side footpath up to Shirley Road ready for asphalt
- Excavated Western side of the road to the underside of the road formation and begin road construction
- LOOK AHEAD
- Begin excavating carriageway to the underside of the road construction and begin filling – We will likely have 2 more days of this next week.
- Construct the Eastern side footpath up to Shirley Road ready for asphalt
- Delays
- Contaminated material to be removed from site slowing down works.
Corde is happy to receive any feedback or concerns from residents.
Take a look at what is happening around Richmond
Te Oraka Community Pools Co-Hosted Fence Removal
Volunteers were back, from different Shirley, Richmond and Dallington groups to remove the Te Oraka Community Pool fence. Kai Pai!
Matariki Decoration Session 2
Second of two workshops to make fabric decorations for our Ururangi tree, celebrating Matariki.
Matariki Decoration Session 1
One of two workshops to make fabric decorations for our Ururangi tree, celebrating Matariki.
History Posters Installed/ Parklet Tidied Stanmore Rd
Finally we have installed the History Panels we have wanted on the corner of Swanns and Stanmore Rd for years. After a proper tidy up a year ago, look at it now!
Adventure Avenue Wander 2025
A wander through the forest and gardens around Richmond and Dallington Red Zone, guided by Hayley Guglietta of Avon Otakaro Network, hosted by We are Richmond.
Te Oraka Community Pools Co-Hosted Cleanup 2&3
Volunteers were back, from different Shirley, Richmond and Dallington groups. Their second and third cleanup sessions at Te Oraka Community Pools were a success!