Stapletons Road (Warden St to Shirley Rd).

  • COMPLETED
    • Begun excavating carriageway to the underside of the road construction and begin filling
    • Constructed the Eastern side footpath up to Shirley Road ready for asphalt
    •  
  • LOOK AHEAD
    • Continue the road dig out on Stapletons Road
    • Seal the footpath up to Shirley Road on Wednesday 21st February – excluding the current crusher dust footpath
    • Begin the Shirley Road tie in works.
    • Begin constructing the road – This will involve the grader and rollers
    •  
  • Delays
    • None.

Take a look at what is happening around Richmond

Matariki 2024 — A Day and Night of Connection

Matariki 2024 — A Day and Night of Connection

Matariki in the Zone was a wonderful day and evening out for our community. A big thank you to Avon-Ōtākaro Network Richmond Community Garden and Avebury House for running this every year! We are Richmond hopped on the bandwagon to help out more this year.   So...

read more