Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 7

Stapletons Road (Warden St to Shirley Rd).
- COMPLETED
- Footpath preparation, ready for asphalt
- Road preparation.
- LOOK AHEAD
- Complete basecourse construction for the road
- Asphalt all footpaths and vehicle crossings.
- Begin installation of raised platform
- Chipseal of road
Take a look at what is happening around Richmond
Families Brighten Up the Vogel Street Alleyway
We Are Richmond team encourages local families to get their artist on
Avon Hub Now Open in Former Spartan Sport Hall
The Avon Hub held an open day 22 May to show the community the sport and meeting facilities now available.
Cultivate comes to Richmond
Richmond locals use Summer with your neighbours fund to celebrate the successful roading outcomes of late
Adventure Ave, a family-friendly environmental playground for kids to enjoy and let their imaginations run wild.
Richmond locals use Summer with your neighbours fund to celebrate the successful roading outcomes of late
Petrie Park Barbecue – Summer with your Neighbours
Richmond locals use Summer with your neighbours fund to celebrate the successful roading outcomes of late
Activities at Richmond Working Men’s Club
Did you know the Richmond Working Men’s club has a Pigeon club!?