Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 8
Stapletons Road (Warden St to Shirley Rd).
- Work completed
- Remediated driveway at No.184
- Completed basecourse construction
- Completed 90% of footpaths and driveway
- Installation of raised platform
- Work planned for the week ahead
- Asphalt final section of footpaths
- Chipseal and asphalting of the road
- Complete berms and landscaping
Take a look at what is happening around Richmond
Stanmore Rd/ Swanns Corner Loved and Refreshed
A group of volunteers from We are Richmond and Peter from River conservation nz helped clean up the overgrown and unloved Stanmore/Swanns Rd corner. Foliage was removed, tidied, cut and the bench seats power-washed and re-stained. Thank you to Keita from Done N...
Richmond Gala 2024–What a Fantastic Day Out!
The Richmond Gala wan an amazing community day. We appreciate everyone coming out and joining in. What amazing work done with all of the massive effort from Avebury House, Richmond Community Garden, and Riverlution We are Richmond is in charge of coordinating the...
Zero Data–Essential websites you can browse Data-Free!
Did you know you can access multiple governmental, school and other essential websites even if you’re out of mobile data? All you need is a device connected to the Spark, Skinny, One NZ, 2degrees, Warehouse Mobile, Slingshot or Orcon mobile networks. The purpose of...
Petrie Park Update December 2023
Petrie Park bowling green remediation is underway and progressing. Hayley Guglietta gives us an update.
RRBA Installs Wayfinding Signs at Swanns Road Parklet
After graffiti damage, these wayfinding community signs have a new lease of life and are now up at the Swanns Road Parklet!
Elmer Elephant Trail Opening Event for Laura Fergusson Brain Injury Trust
The RRBA were honoured to attend Elmer’s Ōtautahi Elephant Trail opening Thursday night and see all of the amazing elephant designs.