• Facebook
We are Richmond
  • Home
  • Local Richmond
    • Active Richmond
    • Educate Richmond
    • Healthy Richmond
    • Tasty Richmond
  • We are Richmond
    • Petrie Park
    • Roading Richmond
    • Membership
    • Civil Defence Plan
  • Blogs
  • Vote Richmond
  • Contact
Select Page
Pickup and Plant at Pareaway Banks Avenue School Entrance

Pickup and Plant at Pareaway Banks Avenue School Entrance

Apr 23, 2026 | Active Richmond, Educate Richmond, Healthy Richmond, Heritage Richmond, RR&BA

Pickup and Plant at Pareaway Banks Avenue School Entrance Last week we partnered with Avon-Ōtākaro Network to plant and tidy this school entryway for Pareawa Banks Ave School!  Thank you to the students, families, and local volunteers for making it happen. We’ll...
Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 8

Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 8

Apr 3, 2024 | Roading in Richmond, RR&BA

Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 8 Stapletons Road (Warden St to Shirley Rd). Work completed Remediated driveway at No.184 Completed basecourse construction Completed 90% of footpaths and driveway Installation of raised platform Work...
Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 7

Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 7

Mar 18, 2024 | Roading in Richmond, RR&BA

Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 7 Stapletons Road (Warden St to Shirley Rd). COMPLETED Footpath preparation, ready for asphalt Road preparation.  LOOK AHEAD Complete basecourse construction for the road Asphalt all footpaths and vehicle...
Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 6

Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 6

Mar 11, 2024 | Roading in Richmond, RR&BA

Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 6 Stapletons Road (Warden St to Shirley Rd). COMPLETED Completed the final kerb pour Subbase construction now fully complete LOOK AHEAD Complete all footpath construction ready for asphalt Complete...
Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 5

Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 5

Mar 4, 2024 | Roading in Richmond, RR&BA

Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 5 Stapletons Road (Warden St to Shirley Rd). COMPLETED Begun the Shirley Road/Stapletons Road intersection construction.  Completed the second stage of road construction up to Shirley Road. Completed the...
« Older Entries

Recent Posts

  • Red Zone Edge Housing Forum
  • Minutes for 26 May 2026
  • Mother of All Cleanups River Cleanup
  • Minutes for 28 April 2026
  • Pickup and Plant at Pareaway Banks Avenue School Entrance