Roadworks Update for Stapletons Road (Warden St to Shirley Rd)

Roadworks Update for Stapletons Road (Warden St to Shirley Rd):
- COMPLETED
- Completed removal of kerb and channel on the Western side.
- Kerb foundation ready to pour next week.
- Drainage 70% completed
- LOOK AHEAD
- Pour the kerb and channel
- Complete drainage
- Begin constructing footpath on the Western side of the road
Corde is happy to receive any feedback or concerns from residents.
Take a look at what is happening around Richmond
Laura Fergusson Brain Injury Trust Groundbreaking Ceremony
Welcome Laura Fergusson Brain Injury Trust to our wider communities. We are excited for your presence in our area.
Te Oraka Community Pools Co-Hosted Fence Removal
Volunteers were back, from different Shirley, Richmond and Dallington groups to remove the Te Oraka Community Pool fence. Kai Pai!
Matariki Decoration Session 2
Second of two workshops to make fabric decorations for our Ururangi tree, celebrating Matariki.
Matariki Decoration Session 1
One of two workshops to make fabric decorations for our Ururangi tree, celebrating Matariki.
History Posters Installed/ Parklet Tidied Stanmore Rd
Finally we have installed the History Panels we have wanted on the corner of Swanns and Stanmore Rd for years. After a proper tidy up a year ago, look at it now!
Adventure Avenue Wander 2025
A wander through the forest and gardens around Richmond and Dallington Red Zone, guided by Hayley Guglietta of Avon Otakaro Network, hosted by We are Richmond.