Dec 1, 2023 | Roading in Richmond, RR&BA

Roadworks Update for the northern Richmond area:

Isaac Construction Update on Progress in Averill Street:
Work is progressing well and it is hoped the major work on the Stapletons/Averill intersection will be finished by the end of this week. Work will then move to the Petrie/Averill intersection next week. Work on the Petrie/Averill intersection will be completed by 22 December.

Stapletons Road rebuild – Warden St to Shirley Road:
Residents in Stapletons Road and nearby including aged care centres, early childhood centres and schools can expect a mail drop from Corde explaining the timeline for the work to begin in this area of Richmond soon. Preliminary surveying work will be done before Christmas and the major reconstruction programme will begin on January 8. Up to date weekly programme schedules will be published on our Facebook site each week so that residents can make plans to cover access to properties during the road closure periods.

Averill Street and Stapletons Road Work Updates 2023/24

Dec 1, 2023 | Roading in Richmond, RR&BA

Take a look at what is happening around Richmond

Red Zone Edge Housing Forum

Red Zone Edge Housing Forum

At the Red Zone Housing Forum, guest speakers covered future Red Zone housing topics, then those attending wrote down what should and shouldn’t be in the Red Zone edge housing areas.

read more
Richmond Gala 2026

Richmond Gala 2026

Our Richmond Gala was another success. Thousands of people came for a great day out. We loved running the Children’s Play Area at Avebury Park.

read more