Chrystal Street Repair Update Week 5
Week 5 Chrystal Street work plan and the key dates and impact below. Information provided by the Isaacs project manager.
We appreciate that everyone has put up with the inconvenience caused by the construction. We are glad to see the new road configuration start to take in shape as most of kerb & channel has been poured.
The focus of next two weeks is on road excavation and pavement construction. We plan to excavate east side of the traffic lane from Tuesday this week. We will continue to provide access to each households at the end of everyday and keep up with the communication.
Important dates | Activity | Impact to residents | Affected households |
Monday, 16 May 2022 | Kerb base construction | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Tuesday, 17 May 2022 | Milling on east side traffic lane | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Wednesday, 18 May 2022 | Milling on east side traffic lane | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Road excavation and backfill | |||
Thursday, 19 May 2022 | Kerb pour & Backfill | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Road excavation and backfill | |||
Friday, 20 May 2022 | Road excavation and backfill | No access to driveway between 7:30am and 5:30pm | All households |
Please note general impact on street residents still applies. |
Take a look at what is happening around Richmond
Roadworks Update for Stapletons Road (Warden St to Shirley Rd)
Roadworks Update for Stapletons Road (Warden St to Shirley Rd): COMPLETED Completed removal of kerb and channel on the Western side. Kerb foundation ready to pour next week. Drainage 70% completed LOOK AHEAD Pour the kerb and channel Complete drainage Begin...
Averill Street and Stapletons Road Work Updates 2023/24
Roadworks Update for the northern Richmond area: Isaac Construction Update on Progress in Averill Street:Work is progressing well and it is hoped the major work on the Stapletons/Averill intersection will be finished by the end of this week. Work will then move to the...
30km/hr Speed Reduction in Richmond–Safe Speed Neighbourhoods
Richmond has been the first suburb to change to 30km per hour speeds on certain streets. Why?
Richmond Roading Update 2023
The representatives of the Richmond Residents and Business Association met recently with the Transport and Roading Group at the Christchurch City Council and we are now able to pass on the following information.................. UPDATE ON IMPROVING THE RICHMOND...