Chrystal Street Repair Update Week 5

May 17, 2022 | Roading in Richmond

Week 5 Chrystal Street work plan and the key dates and impact below. Information provided by the Isaacs project manager.

We appreciate that everyone has put up with the inconvenience caused by the construction. We are glad to see the new road configuration start to take in shape as most of kerb & channel has been poured.

The focus of next two weeks is on road excavation and pavement construction. We plan to excavate east side of the traffic lane from Tuesday this week. We will continue to provide access to each households at the end of everyday and keep up with the communication.

 

Important dates Activity Impact to residents Affected households
Monday, 16 May 2022 Kerb base construction No access to driveway between 7:30am and 5:30pm All households
Stromwater pipe across street
Tuesday, 17 May 2022 Milling on east side traffic lane No access to driveway between 7:30am and 5:30pm All households
Stromwater pipe across street
Wednesday, 18 May 2022 Milling on east side traffic lane No access to driveway between 7:30am and 5:30pm All households
Stromwater pipe across street
Road excavation and backfill
Thursday, 19 May 2022 Kerb pour & Backfill No access to driveway between 7:30am and 5:30pm All households
Stromwater pipe across street
Road excavation and backfill
Friday, 20 May 2022 Road excavation and backfill No access to driveway between 7:30am and 5:30pm All households
Please note general impact on street residents still applies.  

Take a look at what is happening around Richmond

Roadworks Update for Nicholls Street 15

Roadworks Update for Nicholls Street 15

As we progress towards sealing, currently scheduled for 24/5/2024 (weather permitting), we will need the entire street to get our grader, water cart, PTR, roller, trucks running at the same time. If residents require access during the day, we kindly ask that you park...

read more
Roadworks Update for Nicholls Street 14

Roadworks Update for Nicholls Street 14

Two kerb pours are scheduled this week. The first, on Wednesday, is for the North Avon Road Kerb island, with a diamond Traffic management setup for the entire week. Residents of Nicholls Street will not be able to make a right turn onto North Avon Road during this...

read more
Richmond Road Repair Programme Update

Richmond Road Repair Programme Update

We have a recent update from Council about our road building programme which wasstarted in 2018. Currently, work is well underway in Nicholls and Dudley Streets for theStreet renewal project. It is hoped to have a new footpath along the eastern side of NichollsStreet...

read more
Roadworks Update for Nicholls Street 13

Roadworks Update for Nicholls Street 13

Traffic: Nicholls Street, Road closure. The footpath on the west side will remain open until the end of 29/04/24, after which pedestrian access will be switched to the east side. (Residents living on Nicholls st, regarding your access, please check Road Closure...

read more