Chrystal Street Repair Update Week 7

Jun 1, 2022 | Roading in Richmond

Week 7 work plan and the key dates and impact below. Chipseal of the carriageway is Wed 8 June and we will not be able to provide access for vehicles during the sealing, only after 4:30pm.

We’d would like to maintain the road closure to public for the next two weeks and allow time for the new surfacing to settle. The residents can access their houses (enter from Randell St and exit at North Avon Road) while our crew is carrying on the footpath, berm and landscaping on both sides of the street.

 

Important dates Activity Impact to residents Affected households
Monday, 30 May 2022 Road construction No access to driveway between 7:30am and 5:30pm All households
Footpath construction
Tuesday, 31 May 2022 Road construction No access to driveway between 7:30am and 5:30pm All households
Footpath construction
Wednesday, 1 June 2022 Road construction No access to driveway between 7:30am and 5:30pm All households
Footpath construction
Thursday, 2 June 2022 Road construction No access to driveway between 7:30am and 5:30pm All households
Footpath construction
Friday, 3 June 2022 Road construction No access to driveway between 7:30am and 5:30pm All households
Footpath construction
Please note general impact on street residents still applies.