Chrystal Street Repair Update Week 8

Week 8 work plan and the key dates and impact below. We are planning for chipseal tomorrow but will make the final decision in the morning based on the ground temperature and weather forecast. Most of the construction will be finished after the chipseal, we will ramp down to one or two crews working on the footpath, berm and landscaping in the following two to three weeks. On street parking will become available gradually as we complete the footpath and berm/landscaping.
|
Important dates |
Activity |
Impact to residents |
Affected households |
|
Tuesday, 7 June 2022 |
Chipseal |
No access to the street during chipseal |
All households |
|
Footpath construction |
|||
|
Wednesday, 8 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Thursday, 9 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Friday, 10 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Please note general impact on street residents still applies. |
|||
Take a look at what is happening around Richmond
Riverlution Ramble – Explore the Green Spine
We joined Hayley from Avon Otakaro Network on a Riverlution Ramble, showing everything happening in the Red Zone, part of the Walking Festival.
Richmond Gala 2026
Our Richmond Gala was another success. Thousands of people came for a great day out. We loved running the Children’s Play Area at Avebury Park.
Tidy Up Session Medway Parklet
Local neighbours gather together to tidy their corner parklet on Medway Street.
Petrie Park BBQ and Maintenance Session
Neighbours came together to tidy the Petrie Park plantings and to add bark over them. Followed by a community BBQ.