Chrystal Street Repair Update Week 8

Week 8 work plan and the key dates and impact below. We are planning for chipseal tomorrow but will make the final decision in the morning based on the ground temperature and weather forecast. Most of the construction will be finished after the chipseal, we will ramp down to one or two crews working on the footpath, berm and landscaping in the following two to three weeks. On street parking will become available gradually as we complete the footpath and berm/landscaping.
|
Important dates |
Activity |
Impact to residents |
Affected households |
|
Tuesday, 7 June 2022 |
Chipseal |
No access to the street during chipseal |
All households |
|
Footpath construction |
|||
|
Wednesday, 8 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Thursday, 9 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Friday, 10 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Please note general impact on street residents still applies. |
|||
Take a look at what is happening around Richmond
Matariki Community Weaving Session
A morning of meaningful weaving to create kites/ manu tukutuku to decorate our Ururangi Matariki tree.
Red Zone Edge Housing Forum
At the Red Zone Housing Forum, guest speakers covered future Red Zone housing topics, then those attending wrote down what should and shouldn’t be in the Red Zone edge housing areas.
Mother of All Cleanups River Cleanup
Another amazing Mother of All Cleanups along the Avon River. Volunteers from all over came together to clean the river and gather at Riverlution afterwards.
Pickup and Plant at Pareawa Banks Avenue School Entrance April
This school walkway at the Northern entrance of Pareawa Banks Avenue School needs tidying. So we ran a working bee!