Chrystal Street Repair Update Week 9

Please find the attached week 9 work plan and key dates and impact below. As we have completed the chipseal last week, 95% of the work is now completed. The remaining work is footpath, berm, landscaping and linemarking which will be completed over the next two to three weeks.
|
Important dates |
Activity |
Impact to residents |
Affected households |
|
Monday, 13 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Tuesday, 14 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Wednesday, 15 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Thursday, 16 June 2022 |
Footpath construction |
No on street parking |
All households |
|
Friday, 17 June 2022 |
Footpath construction |
No on street parking |
All households |
Take a look at what is happening around Richmond
Tidy Up Session Medway Parklet
Local neighbours gather together to tidy their corner parklet on Medway Street.
Petrie Park BBQ and Maintenance Session
Neighbours came together to tidy the Petrie Park plantings and to add bark over them. Followed by a community BBQ.
Swanns Rd Tidy Up Session with Richmond Community Garden
Richmond Community Garden volunteers worked with We are Richmond to tidy up the Swanns Rd Parklet
Meet-Your-Neighbours Tidy Up Session at Medway Parklet
The Medway Parklet needed a good tidy and local neighbours wanted to meet to see if they could maintain this area in the future.