Petrie / Stapletons / Randall St roadworks
Email update message from Mike Downs (contractor for this work) from Thursday May 9th 2019.
As always, any queries or concerns with this specific work please contact Mike directly or for general concerns via the Richmond residents and business association.
by Craig Given.
Hi Team,
We have approval to reconstruct the last block of Randall Street from Stapletons Rd to Petrie St which will commence on Monday (13th May), weather permitting. I did a letterbox drop for this today (copy attached) advising that we will be closing this block of Randall Street including the Petrie / Randall St intersection from Monday 13th May until we seal these roads in July. Residents will still have access and detours will be clearly signed via Stapletons Rd and Chrystal St.
Also letting you know that the construction work on Chrystal St will be finished by early next week with sealing and asphalting likely to be later next week due to the rain forecast for Sunday & Monday – photos attached.
The planting on Randall St is progressing well – see attached photos. Trees will also be planted will also in Petrie Street early next week.
Kind Regards,
Mike
What other projects are the RR&BA working on?
Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 3
Stapletons Road (Warden St to Shirley Rd). COMPLETED Begun excavating carriageway to the underside of the road construction and begin filling Constructed the Eastern side footpath up to Shirley Road ready for asphalt LOOK AHEAD Continue the road dig out on...
Roadworks Update for Nicholls Street 3
Traffic: Traffic on both Nicholls Street and Dudley street will be organized as one-way, and entry will not bepermitted on North Avon Road and Stapleton Road.Site truck exits the work a zone on Nicholls st towards Dudley with a traffic Controller (TC) who has a...
Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 2
Stapletons Road (Warden St to Shirley Rd) COMPLETED Drainage completed Western side footpath up to Shirley Road ready for asphalt Excavated Western side of the road to the underside of the road formation and begin road construction LOOK AHEAD Begin excavating...
Roadworks Update for Nicholls Street 2
Roadworks Update for Nicholls Street: Currently, the traffic management setup on Nicholls St allows for one-way traffic only from Dudley St towards North Avon Road. However, some residents on Nicholls St are turning in the wrong direction. To ensure everyone's safety,...