Petrie / Stapletons / Randall St roadworks

May 9, 2019 | Roading in Richmond

Email update message from Mike Downs (contractor for this work) from Thursday May 9th 2019.

As always, any queries or concerns with this specific work please contact Mike directly or for general concerns via the Richmond residents and business association.

by Craig Given.

Hi Team,

We have approval to reconstruct the last block of Randall Street from Stapletons Rd to Petrie St which will commence on Monday (13th May), weather permitting. I did a letterbox drop for this today (copy attached) advising that we will be closing this block of Randall Street including the Petrie / Randall St intersection from Monday 13th May until we seal these roads in July. Residents will still have access and detours will be clearly signed via Stapletons Rd and Chrystal St.

Also letting you know that the construction work on Chrystal St will be finished by early next week with sealing and asphalting likely to be later next week due to the rain forecast for Sunday & Monday – photos attached.

The planting on Randall St is progressing well – see attached photos. Trees will also be planted will also in Petrie Street early next week.

Kind Regards,
Mike

What other projects are the RR&BA working on?

2022 Annual AGM Agenda

2022 Annual AGM Agenda

NOTICE of the ANNUAL GENERAL MEETING RICHMOND RESIDENTS’ and BUSINESS ASSOCIATION 30 AUGUST, 7.00 p.m. at AVEBURY HOUSE MEETING AGENDA Welcome and roll call Apologies Minutes of the 2021 Annual General Meeting Chairperson’s Report Financial Report Appointment of...

read more
Richmond shops taking part in Plastic Free July

Richmond shops taking part in Plastic Free July

The month of July was all about reducing your use of single-use plastics. What better way to do this by visiting these local Richmond businesses with alternative options? At all of these businesses, you can bring your own reusable containers/cups, products are...

read more
Petrie Street Repair Update Week 14

Petrie Street Repair Update Week 14

Week 14 Aim of the this week's work will be working to complete the Western side of the street whilst we install the new kerbing and prepare for the new footpath on the Eastern side. We will also complete the installation of the new Stormwater pipes crossing the road....

read more