Petrie / Stapletons / Randall St roadworks
Email update message from Mike Downs (contractor for this work) from Thursday May 9th 2019.
As always, any queries or concerns with this specific work please contact Mike directly or for general concerns via the Richmond residents and business association.
by Craig Given.
Hi Team,
We have approval to reconstruct the last block of Randall Street from Stapletons Rd to Petrie St which will commence on Monday (13th May), weather permitting. I did a letterbox drop for this today (copy attached) advising that we will be closing this block of Randall Street including the Petrie / Randall St intersection from Monday 13th May until we seal these roads in July. Residents will still have access and detours will be clearly signed via Stapletons Rd and Chrystal St.
Also letting you know that the construction work on Chrystal St will be finished by early next week with sealing and asphalting likely to be later next week due to the rain forecast for Sunday & Monday – photos attached.
The planting on Randall St is progressing well – see attached photos. Trees will also be planted will also in Petrie Street early next week.
Kind Regards,
Mike
What other projects are the RR&BA working on?
Nominations Open for We are Richmond
We Are Richmond team encourages local families to get their artist on for a second time
Petrie Street Repair Update Week 12
The aim of the following week will be to complete the entire road excavation. Residents will be moved the West side of the street as we progress with the road construction on the East side. Last week the footpath contained too much moisture for Asphalt sealing, so we...
Chrystal Street Repair Update Planting
From Liam Cai, ISAAC Project Manager: Our landscaping contractor plans to complete the berm and hydroseed today on 2 August. However, due to the wet weather and saturated soil, we have to delay the tree planting when we assess the soil dampness. Currently we’ve...
Petrie Street Repair Update Week 11
This week sees two important milestones. The connection of the water main on North Avon Road and commencing the road construction. The road construction is key to delivering the project on time so expect some additional resource to arrive to site to help with these...