Petrie / Stapletons / Randall St roadworks

May 9, 2019 | Roading in Richmond

Email update message from Mike Downs (contractor for this work) from Thursday May 9th 2019.

As always, any queries or concerns with this specific work please contact Mike directly or for general concerns via the Richmond residents and business association.

by Craig Given.

Hi Team,

We have approval to reconstruct the last block of Randall Street from Stapletons Rd to Petrie St which will commence on Monday (13th May), weather permitting. I did a letterbox drop for this today (copy attached) advising that we will be closing this block of Randall Street including the Petrie / Randall St intersection from Monday 13th May until we seal these roads in July. Residents will still have access and detours will be clearly signed via Stapletons Rd and Chrystal St.

Also letting you know that the construction work on Chrystal St will be finished by early next week with sealing and asphalting likely to be later next week due to the rain forecast for Sunday & Monday – photos attached.

The planting on Randall St is progressing well – see attached photos. Trees will also be planted will also in Petrie Street early next week.

Kind Regards,
Mike

What other projects are the RR&BA working on?

Petrie Street Repair Update Week 8

Petrie Street Repair Update Week 8

As most residents on our street are aware we had anticipated changing our traffic management arrangement this week to help shorten our programme of works. Unfortunately other traffic arrangements in the area has meant we need to put this approach on hold for another...

read more
Petrie Street Repair Update Week 7

Petrie Street Repair Update Week 7

Main aim for week 7 is to allow the watermain advance towards Randall. Having lost one day to rain last week we are anticipating laying the new pipe up to property No.32. The watermain is welded into “strings” each 36m long. We will endeavour to keep them from your...

read more
Petrie Street Repair Update Week 6

Petrie Street Repair Update Week 6

Firstly, I would like to thank the residents for their help and support during week 5 which allowed us to pour the first section of new kerb and channel. It’s always a day of significant disruption and the residents were very helpful and supportive during this...

read more