Petrie / Stapletons / Randall St roadworks

May 9, 2019 | Roading in Richmond

Email update message from Mike Downs (contractor for this work) from Thursday May 9th 2019.

As always, any queries or concerns with this specific work please contact Mike directly or for general concerns via the Richmond residents and business association.

by Craig Given.

Hi Team,

We have approval to reconstruct the last block of Randall Street from Stapletons Rd to Petrie St which will commence on Monday (13th May), weather permitting. I did a letterbox drop for this today (copy attached) advising that we will be closing this block of Randall Street including the Petrie / Randall St intersection from Monday 13th May until we seal these roads in July. Residents will still have access and detours will be clearly signed via Stapletons Rd and Chrystal St.

Also letting you know that the construction work on Chrystal St will be finished by early next week with sealing and asphalting likely to be later next week due to the rain forecast for Sunday & Monday – photos attached.

The planting on Randall St is progressing well – see attached photos. Trees will also be planted will also in Petrie Street early next week.

Kind Regards,
Mike

What other projects are the RR&BA working on?

Chrystal Street Repair Update Week 5

Chrystal Street Repair Update Week 5

Week 5 Chrystal Street work plan and the key dates and impact below. Information provided by the Isaacs project manager. We appreciate that everyone has put up with the inconvenience caused by the construction. We are glad to see the new road configuration start to...

read more
Richmond Road Repair Update

Richmond Road Repair Update

Since a fiery meeting attended by residents and Council staff in 2018, the Richmond Residents’ and Business Association has been collaborating with the City Council with the aim of establishing a step-by-step road repair programme and general upgrade of Richmond...

read more
Methodist Mission Social Housing Units in Guild St

Methodist Mission Social Housing Units in Guild St

There are now 11 homes tenanted with more tenants moving in soon. Currently there are 42 people living at the complex. The Methodist Mission Social Housing staff want to pass on their thanks to the local community for the way they have largely made the new residents...

read more