Petrie Street Repair Update Week 14

Week 14
Aim of the this week’s work will be working to complete the Western side of the street whilst we install the new kerbing and prepare for the new footpath on the Eastern side. We will also complete the installation of the new Stormwater pipes crossing the road.
Pedestrians will remain on the new footpath on the East side.
As Always, if you have any concerns about parking, deliveries you may be expecting, or access/egress issues please see our STMS. Our STMS is the team member in the Green Hi-Vis. He or she will address any of to your concerns
Take a look at what is happening around Richmond
Matariki Decoration Session 1
One of two workshops to make fabric decorations for our Ururangi tree, celebrating Matariki.
History Posters Installed/ Parklet Tidied Stanmore Rd
Finally we have installed the History Panels we have wanted on the corner of Swanns and Stanmore Rd for years. After a proper tidy up a year ago, look at it now!
Adventure Avenue Wander 2025
A wander through the forest and gardens around Richmond and Dallington Red Zone, guided by Hayley Guglietta of Avon Otakaro Network, hosted by We are Richmond.
Te Oraka Community Pools Co-Hosted Cleanup 2&3
Volunteers were back, from different Shirley, Richmond and Dallington groups. Their second and third cleanup sessions at Te Oraka Community Pools were a success!