Petrie Street Repair Update Week 4
Week four sees us getting closer to the end of the street with the Stormwater drainage. The final 80 metres of this pipeline is reinforced concrete so this takes a bit longer as there’s some added detailing involved and concrete pouring around the pipe. Nevertheless, we expect to be down to the last 20m stretch by Friday.
Our behind kerb streetscape crew are busy removing the existing infrastructure and they’re working towards reinstating the first new kerb, planned for Friday.
If you have any concerns about parking, deliveries you may be expecting or access/egress issues please see our STMS. Our STMS is the team member in the Green Hi-Vis. He or she will address any of to your concerns
Week 4: | |||
Important dates | Activity | Impact to residents | Affected households |
Monday, 13 June 2022 | New 300mm Underchannel Stormwater Pipe | One Way system Northbound between North Avon and Randall. Driveway access maintained throughout | All Residents |
Kerb & Footpath Removal | |||
Tuesday, 14 June 2022 | New 300mm Underchannel Stormwater Pipe | One Way system Northbound between North Avon and Randall. Driveway access maintained throughout | All Residents |
Kerb & Footpath Removal | |||
Wednesday, 15 June 2022 | New 300mm Underchannel Stormwater Pipe | One Way system Northbound between North Avon and Randall. Driveway access maintained throughout | All Residents |
Kerb & Footpath Removal | |||
Thursday, 16 June 2022 | New 300mm Underchannel Stormwater Pipe | One Way system Northbound between North Avon and Randall. Driveway access maintained throughout | All Residents |
Kerb & Footpath Removal | |||
Friday, 17 June 2022 | New 300mm Underchannel Stormwater Pipe | One Way system Northbound between North Avon and Randall. Driveway access maintained throughout | All Residents |
Two Concrete Pours | |||
Kerb & Footpath Removal |
Take a look at what is happening around Richmond
Seed Bomb and Seed Packet-Making Workshop
The Richmond community gathered at a bbq at Petrie Park to spend time together but also engage on what they would like to see on the former bowling green at the southern half of the park.
Adventure Avenue Wander/ Walking Festival
The Richmond community gathered at a bbq at Petrie Park to spend time together but also engage on what they would like to see on the former bowling green at the southern half of the park.
Petrie Park Community BBQ & Engagement Session
The Richmond community gathered at a bbq at Petrie Park to spend time together but also engage on what they would like to see on the former bowling green at the southern half of the park.
Safe Speed Neighbourhoods Submission
The implementation of the new speed limits would fit well with the current traffic improvement initiatives in Richmond.