Richmond Roading Update 2023

Feb 15, 2023 | Roading in Richmond

The representatives of the Richmond Residents and Business Association met recently with the Transport and Roading Group at the Christchurch City Council and we are now able to pass on the following information………………

UPDATE ON IMPROVING THE RICHMOND ROADING NETWORK

FULL ROAD RENEWALS 1 – NICHOLLS AND DUDLEY STREETS
Tender process completed by 30 May, 2023
Construction start 1 July, 2023
Construction end 30 November, 2023

FULL ROAD RENEWALS 2 – STAPLETONS ROAD – WARDEN STREET TO SHIRLEY ROAD
Tender process completed by 30 May, 2023
Construction start 1 July, 2023
Construction end 30 September, 2023

RICHMOND CRAF* PROJECTS
 Intersection upgrade at Averill Street and Petrie Street
 Intersection upgrade at Averill Street and Stapletons Road
 Intersection upgrade at Chancellor Street and Guild Street
 Intersection upgrade at Guild Street and Hills Road
 Intersection upgrade at Guild Street and Slater Street
 New kerb and channel on Slater Street from Guild Street to 75/80 Slater
(currently no delineation between road and footpath)
 New speed hump on Slater Street at the Warden Street intersection
 New speed hump on Chancellor Street at the Warden Street intersection
 New speed hump on Dudley Street at the Slater Street intersection
 Slater Street rebuild from Warden Street to Shirley Road
Expected completion date for all of the above – 30 June, 2024
*Christchurch Renewal Amenities Fund (granted by Government in October 2021.)

NEIGHBOURHOOD GREENWAY CYCLEWAY
North Parade, Averill Street, Stapletons Road, Dudley Street, Nicholls Street
Expected completion date – 30 June, 2024

AREA-WIDE SPEED RESTRICTION BETWEEN NORTH AVON ROAD, HILLS ROAD, SHIRLEY ROAD AND
NORTH PARADE
Expected completion date – 30 June, 2023

SLATER STREET REBUILD FROM WARDEN STREET TO SHIRLEY ROAD and no. 80/75
Expected completion date – 30 November, 2024

POULTON AVE
Dates still to be confirmed with pavement maintenance and street trees teams for road resurfacing and tree protection wheel stops work.
All of the above work is supplementary to normal City Council maintenance work. Please use your “Snap, Send, Solve” App to advise the Council of maintenance issues in your street or contact us at secretary@wearerichmond.co.nz>

Take a look at what is happening around Richmond

Richmond Gala 2024–What a Fantastic Day Out!

Richmond Gala 2024–What a Fantastic Day Out!

The Richmond Gala wan an amazing community day. We appreciate everyone coming out and joining in. What amazing work done with all of the massive effort from Avebury House,  Richmond Community Garden, and Riverlution We are Richmond is in charge of coordinating the...

read more
Stanmore Rd/ Swanns Corner Loved and Refreshed

Stanmore Rd/ Swanns Corner Loved and Refreshed

A group of volunteers from We are Richmond and Peter from River conservation nz helped clean up the overgrown and unloved Stanmore/Swanns Rd corner.  Foliage was removed, tidied, cut and the bench seats power-washed and re-stained. Thank you to Keita from Done N...

read more
New Richmond Village Sign Completed

New Richmond Village Sign Completed

What's in a Sign? Well, a lot! After years of deteriorating in the elements, having broken and faded signs, and causing the shopping centre to look run down, We are Richmond decided to do something about the Richmond Village Sign. The shopping centre has no body...

read more
Zero Data–Essential websites you can browse Data-Free!

Zero Data–Essential websites you can browse Data-Free!

Did you know you can access multiple governmental, school and other essential websites even if you’re out of mobile data? All you need is a device connected to the Spark, Skinny, One NZ, 2degrees, Warehouse Mobile, Slingshot or Orcon mobile networks. The purpose of...

read more