Roadworks Update for Nicholls Street 28

12/08/24 – 16/08/24 (Mon- Fri)
•Dudley Street will be completely closed from 7:00 AM to 5:30 PM and will return to one-way traffic after 5:30 PM. We will try our best to accommodate residents on Dudley Street.
If you need daytime access, please approach from Nicholls Street, where a full-time Traffic Controller will be available to assist you.
•Footpath & Driveway prepping on the North side between Slater Street and Stapletons Road.
•Pavers installation at Nicholls & Dudley Junction.
•Reshaping of the Berm & Landscaping on the North side between Nicholls Street & Stapletons Road.
•Footpath on the South side is open to all residents
Site contact person:
Kane Radcliffe, Site supervisor, M:021 830 670
Take a look at what is happening around Richmond
Pickup and Plant at Pareawa Banks Avenue School Entrance August
This school walkway at the Northern entrance of Pareawa Banks Avenue School needs tidying. So we ran a working bee!
Matariki 2026
Matariki 2026 was a beautiful community celebration held in the Richmond Community Garden.
Pickup and Plant at Pareawa Banks Avenue School Entrance June
This school walkway at the Northern entrance of Pareawa Banks Avenue School needs tidying. So we ran a working bee!
Petrie Park Plant and Tidy June Session
Neighbours came together to plant fruit trees and to clean up two crop circles in Petrie Park. Followed by hot soup and a cuppa.
Matariki Community Weaving Session
A morning of meaningful weaving to create kites/ manu tukutuku to decorate our Ururangi Matariki tree.
Red Zone Edge Housing Forum
At the Red Zone Housing Forum, guest speakers covered future Red Zone housing topics, then those attending wrote down what should and shouldn’t be in the Red Zone edge housing areas.