Roadworks Update for Stapletons Road (Warden St to Shirley Rd)

Roadworks Update for Stapletons Road (Warden St to Shirley Rd):
- COMPLETED
- Completed removal of kerb and channel on the Western side.
- Kerb foundation ready to pour next week.
- Drainage 70% completed
- LOOK AHEAD
- Pour the kerb and channel
- Complete drainage
- Begin constructing footpath on the Western side of the road
Corde is happy to receive any feedback or concerns from residents.