Roadworks Update for Stapletons Road (Warden St to Shirley Rd)
Roadworks Update for Stapletons Road (Warden St to Shirley Rd):
- COMPLETED
- Completed removal of kerb and channel on the Western side.
- Kerb foundation ready to pour next week.
- Drainage 70% completed
- LOOK AHEAD
- Pour the kerb and channel
- Complete drainage
- Begin constructing footpath on the Western side of the road
Corde is happy to receive any feedback or concerns from residents.
Take a look at what is happening around Richmond
Petrie Park Mural Painting Event 3
Our second Petrie Park mural painting day with the community was a success, and even the dogs came along!
Petrie Park Mural Painting Event 2
Our second Petrie Park mural painting day with the community was a success, and even the dogs came along!
Petrie Park Mural Painting Event I
We had our first mural painting day with the community and it was a success!
Matariki 2024 — A Day and Night of Connection
Matariki in the Zone was a wonderful day and evening out for our community. A big thank you to Avon-Ōtākaro Network Richmond Community Garden and Avebury House for running this every year! We are Richmond hopped on the bandwagon to help out more this year. So...
Thank you and Farewell to David Duffy
Thank you David for all of your hard work as an integral member of the Richmond Resident’s and Business Association (We Are Richmond) since 2018.
New Richmond Village Sign Completed
What's in a Sign? Well, a lot! After years of deteriorating in the elements, having broken and faded signs, and causing the shopping centre to look run down, We are Richmond decided to do something about the Richmond Village Sign. The shopping centre has no body...