Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 2

Feb 14, 2024 | Roading in Richmond, RR&BA

Stapletons Road (Warden St to Shirley Rd)

  • COMPLETED
    • Drainage completed
    • Western side footpath up to Shirley Road ready for asphalt
    • Excavated Western side of the road to the underside of the road formation and begin road construction
  • LOOK AHEAD
    • Begin excavating carriageway to the underside of the road construction and begin filling – We will likely have 2 more days of this next week.
    • Construct the Eastern side footpath up to Shirley Road ready for asphalt
  • Delays
    • Contaminated material to be removed from site slowing down works.

Corde is happy to receive any feedback or concerns from residents.

Take a look at what is happening around Richmond

Matariki 2024 — A Day and Night of Connection

Matariki 2024 — A Day and Night of Connection

Matariki in the Zone was a wonderful day and evening out for our community. A big thank you to Avon-Ōtākaro Network Richmond Community Garden and Avebury House for running this every year! We are Richmond hopped on the bandwagon to help out more this year.   So...

read more
New Richmond Village Sign Completed

New Richmond Village Sign Completed

What's in a Sign? Well, a lot! After years of deteriorating in the elements, having broken and faded signs, and causing the shopping centre to look run down, We are Richmond decided to do something about the Richmond Village Sign. The shopping centre has no body...

read more