Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 2

Stapletons Road (Warden St to Shirley Rd)
- COMPLETED
- Drainage completed
- Western side footpath up to Shirley Road ready for asphalt
- Excavated Western side of the road to the underside of the road formation and begin road construction
- LOOK AHEAD
- Begin excavating carriageway to the underside of the road construction and begin filling – We will likely have 2 more days of this next week.
- Construct the Eastern side footpath up to Shirley Road ready for asphalt
- Delays
- Contaminated material to be removed from site slowing down works.
Corde is happy to receive any feedback or concerns from residents.