Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 3

Stapletons Road (Warden St to Shirley Rd).
- COMPLETED
- Begun excavating carriageway to the underside of the road construction and begin filling
- Constructed the Eastern side footpath up to Shirley Road ready for asphalt
- LOOK AHEAD
- Continue the road dig out on Stapletons Road
- Seal the footpath up to Shirley Road on Wednesday 21st February – excluding the current crusher dust footpath
- Begin the Shirley Road tie in works.
- Begin constructing the road – This will involve the grader and rollers
- Delays
- None.
Take a look at what is happening around Richmond
Petrie Park Community BBQ & Engagement Session
The Richmond community gathered at a bbq at Petrie Park to spend time together but also engage on what they would like to see on the former bowling green at the southern half of the park.
Safe Speed Neighbourhoods Submission
The implementation of the new speed limits would fit well with the current traffic improvement initiatives in Richmond.
Planting for the Future
Over 360 Pareawa Banks Avenue students and local organisations come together to plant trees for the future.
Rainwater Garden Planting Session on Stanmore Road
Rainwater Garden Brings Beauty to Busy Road
Mayoral Candidate/ Mural Painting Event a Success
We Are Richmond team encourages locals to meet political candidates and paint!
Second Community Painting Event at Vogel Street Alleyway a Success
We Are Richmond team encourages local families to get their artist on for a second time