Guild Street Development Update May 2020

May 29, 2020 | Richmond Urban Plan, RR&BA

Dear RRBA & Local Community

A Water Engineer has today inspected the silt fences located around the perimeter of the site to control rainwater runoff and once we have received the Council’s final approval of these works, the earthworks will commence.  We expect earthmoving machinery to start cutting high points and filling low points tomorrow (Wed 27 May) or at least before the end of this week.  There will be noise as trucks deliver and unload hardfill and excavators load up trucks and trailers for material to be taken away.  Subject to weather and ground conditions, the bulk earthworks will continue for between 6 and 8 weeks.  The Stapletons Road site entrance will be used for these operations and this entrance will be the main entrance during the construction period only.      

Whilst the site will not be operational outside Council permitted times (7am to 6pm Monday to Fridays and 8am to 6pm Saturday), trucks transporting the homes from Linwood Park are required to be on the roads in the early hours of the morning when there is less traffic.  The first two relocatable homes are scheduled to be delivered to the site, most likely via Hills Road, Dudley Street then Stapletons Road, early July – NZTA will need to approve the route and transport times.  The remaining nine pairs of home deliveries (larger homes require 2 transporter trucks and trailers) are scheduled to be transported to site during the month of July.  Once the trucks and trailers are on site, their engines will be turned off and work to lift them onto the foundations will resume from 7am.

Please accept our apologies for the noise that will be emitted from the site and for any inconvenience.  We will send further updates during the construction period and we are always happy to answer any questions.

Kind regards

David

David Kolien

Senior Project Manager

Rangzen-logo-small

Rangzen Projects Limited

m:  027 226 8375

Pop Along and have your say

Petrie Street Repair Update Week 17

Petrie Street Repair Update Week 17

Unfortunately, the footpath asphalt couldn’t get completed this week due to the moisture in the materials. We have reprogramed this for Monday--dependent on the weekend's weather. The aim of this week will be to finish the Eastern side and preparing the road for its...

read more
Petrie Street Repair Update Week 16

Petrie Street Repair Update Week 16

The aim of this week will be to finish the Eastern side, and also planning for preparing the road for its final surface . Pedestrians will remain on the new footpath on the East side. As Always, if you have any concerns about parking, deliveries you may be expecting,...

read more
Petrie Street Repair Update Week 15

Petrie Street Repair Update Week 15

The aim of the following week will be the final touch-ups of the Western side whilst we carry on preparing the footpath and driveway crossings on the Eastern side. We will also be installing the new storm water connections and planting of trees and shrubs along the...

read more
Nominations for RRBA Committee

Nominations for RRBA Committee

Do you want to join a group that takes action to make Richmond a better place to live? Our volunteers work to make positive changes, create relationships, advocate for good in the community, and hold events in our area to improve all residents quality of life.

read more