Feb 19, 2024 | Roading in Richmond, RR&BA
Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 3 Stapletons Road (Warden St to Shirley Rd). COMPLETED Begun excavating carriageway to the underside of the road construction and begin filling Constructed the Eastern side footpath up to Shirley Road...
Feb 14, 2024 | Roading in Richmond, RR&BA
Roadworks Update for Stapletons Road (Warden St to Shirley Rd) 2 Stapletons Road (Warden St to Shirley Rd) COMPLETED Drainage completed Western side footpath up to Shirley Road ready for asphalt Excavated Western side of the road to the underside of the road formation...
Jan 30, 2024 | Roading in Richmond, RR&BA
Roadworks Update for Stapletons Road (Warden St to Shirley Rd) Roadworks Update for Stapletons Road (Warden St to Shirley Rd): COMPLETED Completed removal of kerb and channel on the Western side. Kerb foundation ready to pour next week. Drainage 70% completed LOOK...
Dec 1, 2023 | Roading in Richmond, RR&BA
Averill Street and Stapletons Road Work Updates 2023/24 Roadworks Update for the northern Richmond area: Isaac Construction Update on Progress in Averill Street:Work is progressing well and it is hoped the major work on the Stapletons/Averill intersection will be...