Petrie Park Update December 2023


By Hayley Guglietta
The Petrie Park bowling club remediation is well and truly underway. We have completed the first round of soil testing which has indicated higher than normal levels of arsenic, especially around where the old bowling club shed used to be. High levels of arsenic were expected, given the chemicals used to maintain bowling greens across the country.
If you get a chance, pop on down to the southern half of Petrie Park and check out our progress. There are also signs dotted around the southern portion of the fence.
WE ARE RICHMOND
Mayoral Candidate/ Mural Painting Event a Success
We Are Richmond team encourages locals to meet political candidates and paint!
Petrie Street Repair Update Week 17
Unfortunately, the footpath asphalt couldn’t get completed this week due to the moisture in the materials. We have reprogramed this for Monday--dependent on the weekend's weather. The aim of this week will be to finish the Eastern side and preparing the road for its...
Petrie Street Repair Update Week 16
The aim of this week will be to finish the Eastern side, and also planning for preparing the road for its final surface . Pedestrians will remain on the new footpath on the East side. As Always, if you have any concerns about parking, deliveries you may be expecting,...