The Petrie Park bowling club remediation is well and truly underway. We have completed the first round of soil testing which has indicated higher than normal levels of arsenic, especially around where the old bowling club shed used to be. High levels of arsenic were expected, given the chemicals used to maintain bowling greens across the country.
If you get a chance, pop on down to the southern half of Petrie Park and check out our progress. There are also signs dotted around the southern portion of the fence.
WE ARE RICHMOND
Petrie Street Repair Update Week 4
Week four sees us getting closer to the end of the street with the Stormwater drainage. The final 80 metres of this pipeline is reinforced concrete so this takes a bit longer as there’s some added detailing involved and concrete pouring around the pipe. Nevertheless,...
Chrystal Street Repair Update Planting
From Liam Cai, ISAAC Project Manager: Our landscaping contractor plans to complete the berm and hydroseed today on 2 August. However, due to the wet weather and saturated soil, we have to delay the tree planting when we assess the soil dampness. Currently we’ve...
Chrystal Street Repair Update Week 9
Please find the attached week 9 work plan and key dates and impact below. As we have completed the chipseal last week, 95% of the work is now completed. The remaining work is footpath, berm, landscaping and linemarking which will be completed over the next two to...