Petrie Park Update December 2023
By Hayley Guglietta
The Petrie Park bowling club remediation is well and truly underway. We have completed the first round of soil testing which has indicated higher than normal levels of arsenic, especially around where the old bowling club shed used to be. High levels of arsenic were expected, given the chemicals used to maintain bowling greens across the country.
If you get a chance, pop on down to the southern half of Petrie Park and check out our progress. There are also signs dotted around the southern portion of the fence.
WE ARE RICHMOND
Petrie Street Repair Update Week 8
As most residents on our street are aware we had anticipated changing our traffic management arrangement this week to help shorten our programme of works. Unfortunately other traffic arrangements in the area has meant we need to put this approach on hold for another...
Petrie Street Repair Update Week 7
Main aim for week 7 is to allow the watermain advance towards Randall. Having lost one day to rain last week we are anticipating laying the new pipe up to property No.32. The watermain is welded into “strings” each 36m long. We will endeavour to keep them from your...
Petrie Street Repair Update Week 6
Firstly, I would like to thank the residents for their help and support during week 5 which allowed us to pour the first section of new kerb and channel. It’s always a day of significant disruption and the residents were very helpful and supportive during this...