Petrie Street Repair Update Week 7
Main aim for week 7 is to allow the watermain advance towards Randall. Having lost one day to rain last week we are anticipating laying the new pipe up to property No.32. The watermain is welded into “strings” each 36m long. We will endeavour to keep them from your...
Petrie Street Repair Update Week 6
Firstly, I would like to thank the residents for their help and support during week 5 which allowed us to pour the first section of new kerb and channel. It’s always a day of significant disruption and the residents were very helpful and supportive during this...
Petrie Street Repair Update Week 4
Week four sees us getting closer to the end of the street with the Stormwater drainage. The final 80 metres of this pipeline is reinforced concrete so this takes a bit longer as there’s some added detailing involved and concrete pouring around the pipe. Nevertheless,...