Week 5 Chrystal Street work plan and the key dates and impact below. Information provided by the Isaacs project manager.

We appreciate that everyone has put up with the inconvenience caused by the construction. We are glad to see the new road configuration start to take in shape as most of kerb & channel has been poured.

The focus of next two weeks is on road excavation and pavement construction. We plan to excavate east side of the traffic lane from Tuesday this week. We will continue to provide access to each households at the end of everyday and keep up with the communication.

 

Important dates Activity Impact to residents Affected households
Monday, 16 May 2022 Kerb base construction No access to driveway between 7:30am and 5:30pm All households
Stromwater pipe across street
Tuesday, 17 May 2022 Milling on east side traffic lane No access to driveway between 7:30am and 5:30pm All households
Stromwater pipe across street
Wednesday, 18 May 2022 Milling on east side traffic lane No access to driveway between 7:30am and 5:30pm All households
Stromwater pipe across street
Road excavation and backfill
Thursday, 19 May 2022 Kerb pour & Backfill No access to driveway between 7:30am and 5:30pm All households
Stromwater pipe across street
Road excavation and backfill
Friday, 20 May 2022 Road excavation and backfill No access to driveway between 7:30am and 5:30pm All households
Please note general impact on street residents still applies.  

Take a look at what is happening around Richmond

Petrie Street Repair Update Week 18

Petrie Street Repair Update Week 18

The aim of the following week will be to finish the road construction and complete its final surface . The road closure should only remain in place for 2 more weeks. In the last week, we will complete the line marking and final touch-ups for the handover back to the...

read more
Petrie Street Repair Update Week 17

Petrie Street Repair Update Week 17

Unfortunately, the footpath asphalt couldn’t get completed this week due to the moisture in the materials. We have reprogramed this for Monday--dependent on the weekend's weather. The aim of this week will be to finish the Eastern side and preparing the road for its...

read more
Petrie Street Repair Update Week 16

Petrie Street Repair Update Week 16

The aim of this week will be to finish the Eastern side, and also planning for preparing the road for its final surface . Pedestrians will remain on the new footpath on the East side. As Always, if you have any concerns about parking, deliveries you may be expecting,...

read more
Petrie Street Repair Update Week 15

Petrie Street Repair Update Week 15

The aim of the following week will be the final touch-ups of the Western side whilst we carry on preparing the footpath and driveway crossings on the Eastern side. We will also be installing the new storm water connections and planting of trees and shrubs along the...