Chrystal Street Repair Update Week 5
Week 5 Chrystal Street work plan and the key dates and impact below. Information provided by the Isaacs project manager.
We appreciate that everyone has put up with the inconvenience caused by the construction. We are glad to see the new road configuration start to take in shape as most of kerb & channel has been poured.
The focus of next two weeks is on road excavation and pavement construction. We plan to excavate east side of the traffic lane from Tuesday this week. We will continue to provide access to each households at the end of everyday and keep up with the communication.
Important dates | Activity | Impact to residents | Affected households |
Monday, 16 May 2022 | Kerb base construction | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Tuesday, 17 May 2022 | Milling on east side traffic lane | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Wednesday, 18 May 2022 | Milling on east side traffic lane | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Road excavation and backfill | |||
Thursday, 19 May 2022 | Kerb pour & Backfill | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Road excavation and backfill | |||
Friday, 20 May 2022 | Road excavation and backfill | No access to driveway between 7:30am and 5:30pm | All households |
Please note general impact on street residents still applies. |
Take a look at what is happening around Richmond
Petrie Street Repair Update Week 4
Week four sees us getting closer to the end of the street with the Stormwater drainage. The final 80 metres of this pipeline is reinforced concrete so this takes a bit longer as there’s some added detailing involved and concrete pouring around the pipe. Nevertheless,...
Petrie Street Repair Update Week 3
Week 3 see’s our drainage team pass the 50% complete mark for the new stormwater line. The team will continue straight down Petrie toward No.13. At times this will involve trenching past residents driveways so expect a knock from our friendly staff the evening or...
Chrystal Street Repair Update Week 8
Week 8 work plan and the key dates and impact below. We are planning for chipseal tomorrow but will make the final decision in the morning based on the ground temperature and weather forecast. Most of the construction will be finished after the chipseal, we will ramp...
Chrystal Street Repair Update Week 7
Week 7 work plan and the key dates and impact below. Chipseal of the carriageway is Wed 8 June and we will not be able to provide access for vehicles during the sealing, only after 4:30pm. We’d would like to maintain the road closure to public for the next two weeks...