Chrystal Street Repair Update Week 5
Week 5 Chrystal Street work plan and the key dates and impact below. Information provided by the Isaacs project manager.
We appreciate that everyone has put up with the inconvenience caused by the construction. We are glad to see the new road configuration start to take in shape as most of kerb & channel has been poured.
The focus of next two weeks is on road excavation and pavement construction. We plan to excavate east side of the traffic lane from Tuesday this week. We will continue to provide access to each households at the end of everyday and keep up with the communication.
Important dates | Activity | Impact to residents | Affected households |
Monday, 16 May 2022 | Kerb base construction | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Tuesday, 17 May 2022 | Milling on east side traffic lane | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Wednesday, 18 May 2022 | Milling on east side traffic lane | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Road excavation and backfill | |||
Thursday, 19 May 2022 | Kerb pour & Backfill | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Road excavation and backfill | |||
Friday, 20 May 2022 | Road excavation and backfill | No access to driveway between 7:30am and 5:30pm | All households |
Please note general impact on street residents still applies. |
Take a look at what is happening around Richmond
Petrie Street Repair Update Week 2
Week 2 Petrie Street Works: Important dates Activity Impact to residents Affected households Monday, 30 May 2022 New 300mm Underchannel Stormwater Pipe One Way system Northbound between North Avon and Randall. Driveway access maintained throughout Residents between...
Chrystal Street Repair Update Week 6
Week 6 work plan and the key dates and impact below. We will still focus on road excavation and pavement construction. In addition, we will excavate and install stormwater pipe across the road in front to No. 17 and No. 19. in this week. Important dates...
Richmond Road Repair Update
Since a fiery meeting attended by residents and Council staff in 2018, the Richmond Residents’ and Business Association has been collaborating with the City Council with the aim of establishing a step-by-step road repair programme and general upgrade of Richmond...
RR&BA gets quick action from council after local slips on icy bridge
Community Action gets mesh put on Guild Street bridge