Email update message from Mike Downs (contractor for this work) from Thursday May 9th 2019.

As always, any queries or concerns with this specific work please contact Mike directly or for general concerns via the Richmond residents and business association.

by Craig Given.

Hi Team,

We have approval to reconstruct the last block of Randall Street from Stapletons Rd to Petrie St which will commence on Monday (13th May), weather permitting. I did a letterbox drop for this today (copy attached) advising that we will be closing this block of Randall Street including the Petrie / Randall St intersection from Monday 13th May until we seal these roads in July. Residents will still have access and detours will be clearly signed via Stapletons Rd and Chrystal St.

Also letting you know that the construction work on Chrystal St will be finished by early next week with sealing and asphalting likely to be later next week due to the rain forecast for Sunday & Monday – photos attached.

The planting on Randall St is progressing well – see attached photos. Trees will also be planted will also in Petrie Street early next week.

Kind Regards,
Mike

What other projects are the RR&BA working on?

Richmond shops taking part in Plastic Free July

Richmond shops taking part in Plastic Free July

The month of July was all about reducing your use of single-use plastics. What better way to do this by visiting these local Richmond businesses with alternative options? At all of these businesses, you can bring your own reusable containers/cups, products are...

read more
Nominations for RRBA Committee

Nominations for RRBA Committee

Do you want to join a group that takes action to make Richmond a better place to live? Our volunteers work to make positive changes, create relationships, advocate for good in the community, and hold events in our area to improve all residents quality of life.

read more
Petrie Street Repair Update Week 18

Petrie Street Repair Update Week 18

The aim of the following week will be to finish the road construction and complete its final surface . The road closure should only remain in place for 2 more weeks. In the last week, we will complete the line marking and final touch-ups for the handover back to the...

read more