Guild Street Development Update May 2020

May 29, 2020 | Richmond Urban Plan, RR&BA

Dear RRBA & Local Community

A Water Engineer has today inspected the silt fences located around the perimeter of the site to control rainwater runoff and once we have received the Council’s final approval of these works, the earthworks will commence.  We expect earthmoving machinery to start cutting high points and filling low points tomorrow (Wed 27 May) or at least before the end of this week.  There will be noise as trucks deliver and unload hardfill and excavators load up trucks and trailers for material to be taken away.  Subject to weather and ground conditions, the bulk earthworks will continue for between 6 and 8 weeks.  The Stapletons Road site entrance will be used for these operations and this entrance will be the main entrance during the construction period only.      

Whilst the site will not be operational outside Council permitted times (7am to 6pm Monday to Fridays and 8am to 6pm Saturday), trucks transporting the homes from Linwood Park are required to be on the roads in the early hours of the morning when there is less traffic.  The first two relocatable homes are scheduled to be delivered to the site, most likely via Hills Road, Dudley Street then Stapletons Road, early July – NZTA will need to approve the route and transport times.  The remaining nine pairs of home deliveries (larger homes require 2 transporter trucks and trailers) are scheduled to be transported to site during the month of July.  Once the trucks and trailers are on site, their engines will be turned off and work to lift them onto the foundations will resume from 7am.

Please accept our apologies for the noise that will be emitted from the site and for any inconvenience.  We will send further updates during the construction period and we are always happy to answer any questions.

Kind regards

David

David Kolien

Senior Project Manager

Rangzen-logo-small

Rangzen Projects Limited

m:  027 226 8375

Pop Along and have your say

Chrystal Street Repair Update Week 9

Chrystal Street Repair Update Week 9

Please find the attached week 9 work plan and key dates and impact below. As we have completed the chipseal last week, 95% of the work is now completed. The remaining work is footpath, berm, landscaping and linemarking which will be completed over the next two to...

read more
Petrie Street Repair Update Week 4

Petrie Street Repair Update Week 4

Week four sees us getting closer to the end of the street with the Stormwater drainage. The final 80 metres of this pipeline is reinforced concrete so this takes a bit longer as there’s some added detailing involved and concrete pouring around the pipe. Nevertheless,...

read more
Petrie Street Repair Update Week 3

Petrie Street Repair Update Week 3

Week 3 see’s our drainage team pass the 50% complete mark for the new stormwater line. The team will continue straight down Petrie toward No.13. At times this will involve trenching past residents driveways so expect a knock from our friendly staff the evening or...

read more
Chrystal Street Repair Update Week 8

Chrystal Street Repair Update Week 8

Week 8 work plan and the key dates and impact below. We are planning for chipseal tomorrow but will make the final decision in the morning based on the ground temperature and weather forecast. Most of the construction will be finished after the chipseal, we will ramp...

read more