Whats Happening at the old Churchill Courts Site?

Feb 20, 2020 | Richmond Urban Plan, RR&BA

Invitation from the Christchurch Methodist Mission

Jill Hawkey the Executive Director of the Christchurch Methodist Mission would like to invite you to an information session at Delta Community Trust, 101 North Avon Road, Richmond, Christchurch on Wednesday the 26th February 2020 at 7pm.

There has been much speculation in the community about what will happen to this site, it is a large pocket of land in the middle of a Special Amenities Area.

Anglican Care, as owners of the property, have leased the site to the Christchurch Methodist Mission (CMM) which will be establishing a new housing community there for 15 families.

CMM is working with the Christchurch City Council to integrate the design of the development into the character of the neighbourhood.  The designers have been instructed to enhance the site’s attractive park-like landscape by incorporating fresh plantings and open play spaces for children.

The housing community will feature 11 three-bedroom houses, 2 two-bedroom houses, 2 four-bedroom houses, and a community house.  Several of the properties will be accessible for people with disabilities and the Community House will be available to residents in the neighbourhood for a range of small-group activites.

Work is to start on the site later this month and to be completed in late 2020, with tenants to start  moving in before the end of the year.

 

Pop Along and have your say

Petrie Street Repair Update Week 12

Petrie Street Repair Update Week 12

The aim of the following week will be to complete the entire road excavation. Residents will be moved the West side of the street as we progress with the road construction on the East side. Last week the footpath contained too much moisture for Asphalt sealing, so we...

read more
Chrystal Street Repair Update Planting

Chrystal Street Repair Update Planting

From Liam Cai, ISAAC Project Manager: Our landscaping contractor plans to complete the berm and hydroseed today on 2 August. However, due to the wet weather and saturated soil, we have to delay the tree planting when we assess the soil dampness. Currently we’ve...

read more
Petrie Street Repair Update Week 11

Petrie Street Repair Update Week 11

This week sees two important milestones. The connection of the water main on North Avon Road and commencing the road construction. The road construction is key to delivering the project on time so expect some additional resource to arrive to site to help with these...

read more