Whats Happening at the old Churchill Courts Site?

Feb 20, 2020 | Richmond Urban Plan, RR&BA

Invitation from the Christchurch Methodist Mission

Jill Hawkey the Executive Director of the Christchurch Methodist Mission would like to invite you to an information session at Delta Community Trust, 101 North Avon Road, Richmond, Christchurch on Wednesday the 26th February 2020 at 7pm.

There has been much speculation in the community about what will happen to this site, it is a large pocket of land in the middle of a Special Amenities Area.

Anglican Care, as owners of the property, have leased the site to the Christchurch Methodist Mission (CMM) which will be establishing a new housing community there for 15 families.

CMM is working with the Christchurch City Council to integrate the design of the development into the character of the neighbourhood.  The designers have been instructed to enhance the site’s attractive park-like landscape by incorporating fresh plantings and open play spaces for children.

The housing community will feature 11 three-bedroom houses, 2 two-bedroom houses, 2 four-bedroom houses, and a community house.  Several of the properties will be accessible for people with disabilities and the Community House will be available to residents in the neighbourhood for a range of small-group activites.

Work is to start on the site later this month and to be completed in late 2020, with tenants to start  moving in before the end of the year.

 

Pop Along and have your say

Chrystal Street Repair Update Week 9

Chrystal Street Repair Update Week 9

Please find the attached week 9 work plan and key dates and impact below. As we have completed the chipseal last week, 95% of the work is now completed. The remaining work is footpath, berm, landscaping and linemarking which will be completed over the next two to...

read more
Petrie Street Repair Update Week 4

Petrie Street Repair Update Week 4

Week four sees us getting closer to the end of the street with the Stormwater drainage. The final 80 metres of this pipeline is reinforced concrete so this takes a bit longer as there’s some added detailing involved and concrete pouring around the pipe. Nevertheless,...

read more
Petrie Street Repair Update Week 3

Petrie Street Repair Update Week 3

Week 3 see’s our drainage team pass the 50% complete mark for the new stormwater line. The team will continue straight down Petrie toward No.13. At times this will involve trenching past residents driveways so expect a knock from our friendly staff the evening or...

read more
Chrystal Street Repair Update Week 8

Chrystal Street Repair Update Week 8

Week 8 work plan and the key dates and impact below. We are planning for chipseal tomorrow but will make the final decision in the morning based on the ground temperature and weather forecast. Most of the construction will be finished after the chipseal, we will ramp...

read more