Sep 9, 2024 | Roading in Richmond, RR&BA
Final Roadworks Update for Nicholls Street 30 As we approach the final stage of the project, Higgins would like to take a moment to express our sincere gratitude for your patience, understanding, and support throughout the entire process. We know that the disruptions...
Aug 26, 2024 | Roading in Richmond, RR&BA
Roadworks Update for Nicholls Street 29 26/08/24 – 30/08/24 (Mon- Fri) • Traffic management:Dudley street:Two lanes open between Nicholls Street and Slater Street. Both sides of footpaths on Dudley Street are open7am-6pm Stapletons Road/Dudley St intersection road...
Aug 12, 2024 | Roading in Richmond, RR&BA
Roadworks Update for Nicholls Street 28 12/08/24 – 16/08/24 (Mon- Fri) •Dudley Street will be completely closed from 7:00 AM to 5:30 PM and will return to one-way traffic after 5:30 PM. We will try our best to accommodate residents on Dudley Street. If you need...
Aug 5, 2024 | Roading in Richmond, RR&BA
Roadworks Update for Nicholls Street 27 You might see that there are bits of works happening along the new Hydroseeded berm section along Nicholls Street. We have ZM contracting, our subcontractor, boxing up the 9×5 inspection box for concrete pouring which will...
Jul 30, 2024 | Roading in Richmond, RR&BA
Roadworks Update for Nicholls Street 26 As you can see, new hydroseeding and nursery plants and trees have been planted on Nicholls Street. The greenery is making Nicholls Street look lovely, so let’s protect it by avoiding stepping on it. With Dudley Street...