Chrystal Street Repair Update Week 5
Week 5 Chrystal Street work plan and the key dates and impact below. Information provided by the Isaacs project manager.
We appreciate that everyone has put up with the inconvenience caused by the construction. We are glad to see the new road configuration start to take in shape as most of kerb & channel has been poured.
The focus of next two weeks is on road excavation and pavement construction. We plan to excavate east side of the traffic lane from Tuesday this week. We will continue to provide access to each households at the end of everyday and keep up with the communication.
Important dates | Activity | Impact to residents | Affected households |
Monday, 16 May 2022 | Kerb base construction | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Tuesday, 17 May 2022 | Milling on east side traffic lane | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Wednesday, 18 May 2022 | Milling on east side traffic lane | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Road excavation and backfill | |||
Thursday, 19 May 2022 | Kerb pour & Backfill | No access to driveway between 7:30am and 5:30pm | All households |
Stromwater pipe across street | |||
Road excavation and backfill | |||
Friday, 20 May 2022 | Road excavation and backfill | No access to driveway between 7:30am and 5:30pm | All households |
Please note general impact on street residents still applies. |
Take a look at what is happening around Richmond
Petrie Street Repair Update Week 8
As most residents on our street are aware we had anticipated changing our traffic management arrangement this week to help shorten our programme of works. Unfortunately other traffic arrangements in the area has meant we need to put this approach on hold for another...
Petrie Street Repair Update Week 7
Main aim for week 7 is to allow the watermain advance towards Randall. Having lost one day to rain last week we are anticipating laying the new pipe up to property No.32. The watermain is welded into “strings” each 36m long. We will endeavour to keep them from your...
Petrie Street Repair Update Week 6
Firstly, I would like to thank the residents for their help and support during week 5 which allowed us to pour the first section of new kerb and channel. It’s always a day of significant disruption and the residents were very helpful and supportive during this...
Chrystal Street Repair Update Week 9
Please find the attached week 9 work plan and key dates and impact below. As we have completed the chipseal last week, 95% of the work is now completed. The remaining work is footpath, berm, landscaping and linemarking which will be completed over the next two to...