Petrie Street Repair Update Week 4

Petrie Street Repair Update Week 4

Petrie Street Repair Update Week 4 Week four sees us getting closer to the end of the street with the Stormwater drainage. The final 80 metres of this pipeline is reinforced concrete so this takes a bit longer as there’s some added detailing involved and concrete...
Petrie Street Repair Update Week 3

Petrie Street Repair Update Week 3

Petrie Street Repair Update Week 3 Week 3 see’s our drainage team pass the 50% complete mark for the new stormwater line. The team will continue straight down Petrie toward No.13. At times this will involve trenching past residents driveways so expect a knock from our...
Chrystal Street Repair Update Week 8

Chrystal Street Repair Update Week 8

Chrystal Street Repair Update Week 8 Week 8 work plan and the key dates and impact below. We are planning for chipseal tomorrow but will make the final decision in the morning based on the ground temperature and weather forecast. Most of the construction will be...
Chrystal Street Repair Update Week 7

Chrystal Street Repair Update Week 7

Chrystal Street Repair Update Week 7 Week 7 work plan and the key dates and impact below. Chipseal of the carriageway is Wed 8 June and we will not be able to provide access for vehicles during the sealing, only after 4:30pm. We’d would like to maintain the road...
Families Brighten Up the Vogel Street Alleyway

Families Brighten Up the Vogel Street Alleyway

Families Brighten Up the Vogel Street Alleyway On 28 May, families from the Richmond community and beyond gathered in the alleyway between Evelyn Couzins Avenue and Vogel Street to brighten the corrugated iron fence with garden insects. This event was run by We are...