Chrystal Street Repair Update Planting

Chrystal Street Repair Update Planting

Chrystal Street Repair Update Planting From Liam Cai, ISAAC Project Manager: Our landscaping contractor plans to complete the berm and hydroseed today on 2 August. However, due to the wet weather and saturated soil, we have to delay the tree planting when we assess...
Chrystal Street Repair Update Week 9

Chrystal Street Repair Update Week 9

Chrystal Street Repair Update Week 9 Please find the attached week 9 work plan and key dates and impact below. As we have completed the chipseal last week, 95% of the work is now completed. The remaining work is footpath, berm, landscaping and linemarking which will...
Chrystal Street Repair Update Week 8

Chrystal Street Repair Update Week 8

Chrystal Street Repair Update Week 8 Week 8 work plan and the key dates and impact below. We are planning for chipseal tomorrow but will make the final decision in the morning based on the ground temperature and weather forecast. Most of the construction will be...
Chrystal Street Repair Update Week 7

Chrystal Street Repair Update Week 7

Chrystal Street Repair Update Week 7 Week 7 work plan and the key dates and impact below. Chipseal of the carriageway is Wed 8 June and we will not be able to provide access for vehicles during the sealing, only after 4:30pm. We’d would like to maintain the road...
Chrystal Street Repair Update Week 6

Chrystal Street Repair Update Week 6

Chrystal Street Repair Update Week 6 Week 6 work plan and the key dates and impact below.  We will still focus on road excavation and pavement construction. In addition, we will excavate and install stormwater pipe across the road in front to No. 17 and No. 19. in...