Richmond blog
Petrie Street Repair Update Week 15
The aim of the following week will be the final touch-ups of the Western side whilst we carry on preparing the footpath and driveway crossings on...
Richmond shops taking part in Plastic Free July
The month of July was all about reducing your use of single-use plastics. What better way to do this by visiting these local Richmond businesses...
Petrie Street Repair Update Week 14
Week 14 Aim of the this week's work will be working to complete the Western side of the street whilst we install the new kerbing and prepare for the...
Petrie Street Repair Update Week 12
The aim of the following week will be to complete the entire road excavation. Residents will be moved the West side of the street as we progress...
Chrystal Street Repair Update Planting
From Liam Cai, ISAAC Project Manager: Our landscaping contractor plans to complete the berm and hydroseed today on 2 August. However, due to the wet...
Minutes July 2022
Minutes of the Meeting held over Zoom, Tuesday, 26 July, 2022 Present: H.Guglietta (Chair), Committee Members: D.Duffy, Secretary: R....
Petrie Street Repair Update Week 11
This week sees two important milestones. The connection of the water main on North Avon Road and commencing the road construction. The road...
Second Community Painting Event at Vogel Street Alleyway a Success
On 14 July, families from the Richmond community gathered in the alleyway between Evelyn Couzins Avenue and Vogel Street for a second time to...
Minutes June 2022
Minutes of the Meeting held at Richmond Club, Tuesday, 28 June, 2022 Present: M.James (Chair/Treasurer) Committee Members: C. Given,...
Minutes May 2022
Minutes of the Meeting held at Avebury House, Tuesday, 24 May, 2022 Present: M.James (Chair/Treasurer) Committee Members: C. Given, D.Duffy,...
Petrie Street Repair Update Week 8
As most residents on our street are aware we had anticipated changing our traffic management arrangement this week to help shorten our programme of...
Petrie Street Repair Update Week 7
Main aim for week 7 is to allow the watermain advance towards Randall. Having lost one day to rain last week we are anticipating laying the new pipe...
Petrie Street Repair Update Week 6
Firstly, I would like to thank the residents for their help and support during week 5 which allowed us to pour the first section of new kerb and...
Chrystal Street Repair Update Week 9
Please find the attached week 9 work plan and key dates and impact below. As we have completed the chipseal last week, 95% of the work is now...
Petrie Street Repair Update Week 4
Week four sees us getting closer to the end of the street with the Stormwater drainage. The final 80 metres of this pipeline is reinforced concrete...
Petrie Street Repair Update Week 3
Week 3 see’s our drainage team pass the 50% complete mark for the new stormwater line. The team will continue straight down Petrie toward No.13. At...
Chrystal Street Repair Update Week 8
Week 8 work plan and the key dates and impact below. We are planning for chipseal tomorrow but will make the final decision in the morning based on...
Chrystal Street Repair Update Week 7
Week 7 work plan and the key dates and impact below. Chipseal of the carriageway is Wed 8 June and we will not be able to provide access for...















