Minutes May 2022

Minutes May 2022

Minutes of the Meeting held at Avebury House, Tuesday, 24 May, 2022   Present: M.James (Chair/Treasurer) Committee Members: C. Given, D.Duffy,...

Petrie Street Repair Update Week 8

Petrie Street Repair Update Week 8

As most residents on our street are aware we had anticipated changing our traffic management arrangement this week to help shorten our programme of...

Petrie Street Repair Update Week 7

Petrie Street Repair Update Week 7

Main aim for week 7 is to allow the watermain advance towards Randall. Having lost one day to rain last week we are anticipating laying the new pipe...

Petrie Street Repair Update Week 6

Petrie Street Repair Update Week 6

Firstly, I would like to thank the residents for their help and support during week 5 which allowed us to pour the first section of new kerb and...

Chrystal Street Repair Update Week 9

Chrystal Street Repair Update Week 9

Please find the attached week 9 work plan and key dates and impact below. As we have completed the chipseal last week, 95% of the work is now...

Petrie Street Repair Update Week 4

Petrie Street Repair Update Week 4

Week four sees us getting closer to the end of the street with the Stormwater drainage. The final 80 metres of this pipeline is reinforced concrete...

Petrie Street Repair Update Week 3

Petrie Street Repair Update Week 3

Week 3 see’s our drainage team pass the 50% complete mark for the new stormwater line. The team will continue straight down Petrie toward No.13. At...

Chrystal Street Repair Update Week 8

Chrystal Street Repair Update Week 8

Week 8 work plan and the key dates and impact below. We are planning for chipseal tomorrow but will make the final decision in the morning based on...

Chrystal Street Repair Update Week 7

Chrystal Street Repair Update Week 7

Week 7 work plan and the key dates and impact below. Chipseal of the carriageway is Wed 8 June and we will not be able to provide access for...

Petrie Street Repair Update Week 2

Petrie Street Repair Update Week 2

Week 2 Petrie Street Works: Important dates Activity Impact to residents Affected households Monday, 30 May 2022 New 300mm Underchannel Stormwater...

Chrystal Street Repair Update Week 6

Chrystal Street Repair Update Week 6

Week 6 work plan and the key dates and impact below.  We will still focus on road excavation and pavement construction. In addition, we will...

Chrystal Street Repair Update Week 5

Chrystal Street Repair Update Week 5

Week 5 Chrystal Street work plan and the key dates and impact below. Information provided by the Isaacs project manager. We appreciate that everyone...

Minutes April 2022

Minutes April 2022

Minutes of the Meeting held at Richmond Club, Tuesday, 22 March, 2022 Present: Committee:H.Guglietta (chair), M.James (treasurer)Committee Members:...

Laura Fergusson Trust Comes to Richmond

Laura Fergusson Trust Comes to Richmond

On April 11, the Laura Fergusson Trust held an informal gathering in the grounds of the old site of Marian College. A group from "We Are Richmond"...

Minutes March 2022

Minutes March 2022

Minutes of the Meeting held at Richmond Club, Tuesday, 22 March, 2022 Present: Committee: H.Guglietta (chair), M.James (treasurer), C. Given....

Richmond Road Repair Update

Richmond Road Repair Update

Since a fiery meeting attended by residents and Council staff in 2018, the Richmond Residents’ and Business Association has been collaborating with...